| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
During the EIS Process a portion of the conceptual and preliminary engineering and design was completed. This was done in order to test the practicality of the concepts that were introduced through the alternative development process. This alternative evaluation phase was carried out concurrent with the other EIS processes. Conceptual design encompassed the Alternative Development and Screening processes and was crucial in determining how well a proposed alternative was able to meet the Purpose and Need of the project and what type and degree of environmental impacts were associated with it. It was during conceptual engineering that the alternatives were evaluated based on ability to correct existing roadway deficiencies as stated in the project Purpose and Need and to meet current highway design standards with minimal environmental impact. Alternatives that cannot meet these criteria were eliminated from the process and those that were determined to be reasonable were studied in greater depth.
When feasible alternatives were identified for the various portions of the project, they were grouped into reasonable alternative packages fulfilled the overall project objectives. These packages, also known as "system alternatives", then underwent a final evaluation and comparison in order to select the final "Preferred Alternative" for the corridor. When the Preferred Alternative was selected, as much as 30% of the preliminary design work had been completed and the Preferred Alternative is ready to proceed into final design and then into construction.
Alternative Development and Screening
Alternatives were developed with an emphasis on the "interchange nodes" along the corridor (I-25 interchanges with Broadway, Santa Fe, Alameda Ave. and 6th Ave., and 6th Avenue Interchanges with Bryant St., and Federal Blvd.). In addition, alternatives for the alignment of I-25 and alternatives for the grade separation of the railroad crossing at Kalamath/Santa Fe were developed. More than 80 alternatives were presented at the December 2002 Public Meetings.
Screening of Alternatives - Initial Screening for Reasonableness and Practicalbility
Compatibility Testing
Detailed Alternatives Map and Alternatives Information
The remaining 15 interchange alternatives and the I-25 mainline alternative were packaged into “system alternatives". A system alternative is a combination of interchange and mainline alternatives that is able to fulfill the project Purpose and Need for the project corridor (I-25 from Logan St. to 6th Ave. and 6th Ave. from I-25 to Federal Blvd.). Four system alternatives were developed from 13 of the 15 remaining interchange alternatives and the I-25 mainline alternative. Additionally, the No Action Alternative, must be included in the EIS evaluation. These system alternatives were proposed to the public in July 2003 for review and comment. Building on comments received at that meeting and further consolidation of alternatives to achieve specific goals, four alternatives were advanced for more detailed environmental study in the Draft EIS. The four system alternatives were as follows:
These alternatives were fully evaluated in the Draft EIS with regard to transportation benefits and environmental considerations. Identification of the Preferred Alternative In the Final EIS, CDOT and FHWA identified a Preferred Alternative for the Valley Highway Project that combines elements of the three system alternates that were analyzed in the Draft EIS. The Preferred Alternative does not represent a new alternative, but rather a refinement based in the analysis contained in the Draft EIS and comments received from the public and agencies. The Preferred Alternative includes the following major elements:
Following identification of the major elements of the Preferred Alternative, CDOT and FHWA reviewed the elements in light of comments that had been received on the Draft EIS to establish whether any refinements should be made to the elements to address specific concerns. This resulted in a number of refinements being made to the Preferred Alternative, as follows:
These refinements have been included in the Preferred Alternative as presented and analyzed in this Final EIS. The Preferred Alternative balances transportation improvements with social and environmental considerations. CDOT and FHWA have concluded that the Preferred Alternative:
Design of the Final Preferred Alternative As part of the NEPA EIS process, the Valley Highway EIS Study took into account other existing and planned transportation projects. To assure continuity with other ongoing planning efforts, the CDOT Project Manager met monthly with RTD, City and County of Denver, and DRCOG representatives about the Valley Highway Corridor and the need to coordinate actions and reduce impacts. CDOT also met regularly with representatives from Cherokee Denver and Gates to address the increase in traffic volumes expected from redevelopment of the Gates property. Design and Technology - improving the national highway system
Click to read Design and Technology for information, insight and links to learn more about the ever improving design and safety standards of the national highway system. Read why reconstruction of older portions of the system is necessary, how design standards have advanced with advances in technology, and how information about system usage is used to make the system safer and more cost effective.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||